Resource Planner – QA & Bug Fixing

Story: Resource Planner – QA & Bug Fixing

Description:

We have developed the Resource Planner module. Now we need to ensure all modules are bug-free and QA approved.

Scope:

  • QA team should test all features and modules in Resource Planner thoroughly.
  • Developers and QA should connect and solve all bugs found during testing.
  • Bugs in existing features like filters and other functionalities must be fixed before moving to new changes or enhancements.

Important Note for QA:

⚠️ Before giving any new changes or suggestions, confirm with the PM.

Acceptance Criteria:

✅ All bugs in Resource Planner are fixed

✅ QA has tested and approved all modules

✅ Filters and other existing features are working properly without issues

✅ No critical or major bugs pending after this cycle

Comments

6 responses to “Resource Planner – QA & Bug Fixing”

  1. gaurav.golecha@diginnovators.com Avatar
    gaurav.golecha@diginnovators.com

    Rajilesh & Saahil discuss

    & add time lines here

  2. sahil.sute@diginnovators.com Avatar
    sahil.sute@diginnovators.com

    1 to 2 hours for retesting this all bugs @gaurav

  3. rajilesh.panoli@diginnovators.com Avatar
    rajilesh.panoli@diginnovators.com

    Points are not clear. Please explain what you mean by hover effect?

  4. rajilesh.panoli@diginnovators.com Avatar
    rajilesh.panoli@diginnovators.com

    https://prnt.sc/bnTNzG9x0HEl

    What is the issue here?

  5. rajilesh.panoli@diginnovators.com Avatar
    rajilesh.panoli@diginnovators.com

    cannot reproduce this. https://prnt.sc/1Ebgf2BYt5se

  6. rajilesh.panoli@diginnovators.com Avatar
    rajilesh.panoli@diginnovators.com

    Sahil, you can let me know once all testings are done, then I’ll add my time there